CICADA CREST APARTMENTS

As at Sep-2023

Contractor: Johkab Enterprises Ltd
Project Start Date: 1st March 2019
Expected Construction Period: 160 Weeks
Project Outline: Construction of 120 units: two blocks each with 60 units in Kilimani
91%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Casting of the 16th floor slab is 100% done.
Casting of the water tank slab, and machine room for the lift is expected to be done 100%.
First fixes to both mechanical and electrical services have been achieved to the rooftop slab (16th Floor) i.e. 100% done.
Electrical and mechanical first fixes to be done for the parapet wall.
Construction of the walls at the 14th floor is at 92%.
Completion of structural skeleton and shell i.e. Concrete and Masonry works
Hacking for both electrical and mechanical provisions in the walls before plaster works commences for 7th to 9th floors is currently ongoing at 95%.
Electrical and mechanical first fixes to Roof slab and as for the walls 6th to 9th floor.
Setting of external plaster works was done for all the levels.
Start on production of the wooden doors, joinery and Aluminium windows.

KENZI RESIDENCE

As at Sep-2023

Contractor: Nels Enterprise Limited
Project Start Date: October 2021
Expected Construction Period: 140 Weeks
Project Outline: Construction of 112 units, 5 parking levels along School Lane Road
33%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Steel fixing to columns projecting to the second floor is 100% done.
Steel fixing to columns projecting to the sixth and seventh floors are to be done 100%.
Formwork to the vertical members projecting to the fifth floor slab : columns, shear walls and lift shafts were done .
Formwork to the vertical members projecting to sixth and seventh : columns, shear walls and lift shafts to be 100% done.
Decking formwork for the fifth floor slab was 100% done.
Decking formwork for the sixth and seventh floor slabs are to be done 100%.
Steel cutting, bending and fixing to the fifth floor slab was done 100%.
Steel cutting, bending and fixing to the sixth and seventh floor slab to be done 100%.

COVO COMMERCIAL- LAVINGTON

As at Sep-2023

Contractor: Hari International
Project Start Date: 23rd February 2021
Expected Construction Period: 64 Weeks
Project Outline: Construction of a 3 floors commercial hub in Lavington.
98%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Installation of transformer slab, and delivery of transformer by Kplc is currently ongoing.
Kplc prepaid meters are expected to be delivered 100%.
External Manholes, and storm water disposal grating to the open channel is 100% done.
Fittings of gate valves and plumbing accessories to be 100% done
Installation of high end CCTV surveillance cameras have started doing setting of points.
Tiling works on ground, first and second floor walkways to be done.
Washroom fittings and partitioning is in progress at 75%
Gypsum ceiling, washroom partitions and the light fixtures to be done
Paint work to Basement walls is 100% done
Paint works to Basement parking markings to be 100% done.

COVO RESIDENTIAL -LAVINGTON

As at Sep-2023

Contractor: Hari International
Project Start Date: 23rd February, 2021
Expected Construction Period: 169 Weeks
Project Outline: Construction of 120 units in Lavington
48%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Preparations of Columns Reinforcements, Formworks and casting to columns projecting to 7th Floor slab is on going.
Preparations of Columns Reinforcements, Formworks and casting to columns projecting to 7th Floor slab is on going.
Steel fixing and casting for Shear walls, and lift shaft projecting to the 7th floor were done 100%.
Steel fixing and casting for Shear walls, and lift shaft projecting to the 8th floor to be done.
Walling to the fourth typical floor is 30% done.
Walling to the fourth typical floor is expected to be 100% done.
Mechanical and Electrical first fixes to the third typical slab and walls are 100% done.
Mechanical and Electrical first fixes to the fourth typical walls to be 100% done.