CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Installation of transformer slab, and delivery of transformer by Kplc is currently ongoing.
Kplc prepaid meters are expected to be delivered 100%.
External Manholes, and storm water disposal grating to the open channel is 100% done.
Fittings of gate valves and plumbing accessories to be 100% done
Installation of high end CCTV surveillance cameras have started doing setting of points.
Tiling works on ground, first and second floor walkways to be done.
Washroom fittings and partitioning is in progress at 75%
Gypsum ceiling, washroom partitions and the light fixtures to be done
Paint work to Basement walls is 100% done
Paint works to Basement parking markings to be 100% done.