CICADA CREST APARTMENTS

As at Oct-2023

Contractor: Johkab Enterprises Ltd
Project Start Date: 1st March 2019
Expected Construction Period: 160 Weeks
Project Outline: Construction of 120 units: two blocks each with 60 units in Kilimani
91%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Hacking for both electrical and mechanical provisions in the walls for 7th to 9th floor currently ongoing at 95%.
Electrical and mechanical first fixes to Roof slab and as for the walls 6th to 9th floor.
Walling at 15th floor wing A done 75% done.
Walling to 15th floor Wing A to be done 100%
Setting of external plaster works done for all levels.
External plaster works to be done 100%
Plaster work done to 7th floor.
Plaster work to 15 floor to be done 100%

KENZI RESIDENCE

As at Oct-2023

Contractor: Nels Enterprises Limited
Project Start Date: October 2021
Expected Construction Period: 140 Weeks
Project Outline: Construction of 112 units, 5 parking levels at Westland’s School Lane Road
33%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Steel fixing to columns projecting to the 7th floor done 100%
Steel fixing of columns projecting to 8th and 9th floor to be 100%done.
Formwork to the vertical members projecting to the 5th floor slab; columns, shear walls and lift shafts done 100%
Formwork to the vertical members projecting to the 8th and 9th floor; columns, shear walls and lift shafts to be 100% done.
Casting of all the columns and shear walls projecting to the 6th and 7th floor done 100%
Casting of all the columns and shear walls are to be done 100%
Decking formwork for the 6th and 7th floor done 100%
Decking formwork for the 8th and 9th floor slabs to be done 100%
Steel cutting, bending and fixing to 7th floor done 100%
Steel cutting, bending and fixing to the 9th floor to be done 100%

COVO SQUARE - LAVINGTON

As at Oct-2023

Contractor: Hari International Ltd
Project Start Date: 23rd February, 2021
Expected Construction Period: 64 Weeks
Project Outline: Construction of a 3 floors commercial hub in Lavington
98%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Installation of transformer slab, and delivery of transformer by KPLC is currently ongoing.
KPLC prepaid meters are expected to be delivered 100%
Gypsum ceiling, washroom partitions and light fixtures are ongoing at 1st floor.
Gypsum ceiling, washroom partitions and the light fixtures to be done 100%
Fittings of gate valves and plumbing accessories were 100% done to all shops.
Tiling works on ground, 1st and 2nd floor walkways to be done 100%
Paint works to basement one parking markings are ongoing.
Paint works to basement parking markings to be done 100%

COVO RESIDENTIAL - LAVINGTON

As at Oct-2023

Contractor: Hari International Ltd
Project Start Date: 23rd February, 2021
Expected Construction Period: 169 Weeks
Project Outline: Construction of 120 residential units in Lavington
48%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Preparations of column reinforcements, formworks and casting to columns projecting to 8th floor slab has been casted.
Preparations of 9th floor slab decking reinforcements, formworks and casting to columns projecting to 9th floor to be done 100%
Steel fixing and casting for sheer walls, and lift shaft projecting to 8th floor done 100%
Steel fixing and casting for sheer walls, and lift shaft projecting to 9th floor done 100%
Casting of the 8th floor slab has been achieved 100%
Preparation and casting of the 9th and 10th floor slabs to be done 100%
Walling to 5th typical floor ongoing.
Walling to 6th typical floor to be done 100%
Mechanical and electrical first fixes to the 3rd typical slab and walls done 100%
Mechanical and electrical first fixes to the 4th typical walls to be 100% done.

COVO ARBORETUM

As at Oct-2023

Contractor: Johkab Enterprises Ltd (Excavating Contractor)
Project Start Date: September 2023
Expected Construction Period: 125 Weeks
Project Outline: Construction of 287 residential units and 220 commercial units along Ring Road Kileleshwa
1%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Excavation process ongoing
Excavation to be 100% done