CICADA CREST APARTMENTS

As at May-2023

Contractor: Johkab Enterprises
Project Start Date: 1st March 2019
Expected Construction Period: 160 weeks
Project Outline: Construction of 120 units: two blocks each with 60 units in Kilimani
90%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
•Reinforcement and formworks to columns to the 15th floor wing B done 98%.
•Formworks and reinforcement to columns to the 14th floor to be 100% done.
•Formworks to the 15th floor wing B completed 95%
•Reinforcement and casting of the 11th floor section B to be 100% done.
•Walling on the done on the 9th & 10th floor
•Walling on the 11th & 12th floor to be 80%
•Lift walls done up to the 15th floor wing A&B.
•Lift walls to be casted to the 11th floor level.
•Plaster works to proceed on the 6th & 7th floor.
•Plaster works to the 7th & 8th floor units Section A to be 100% done.

COVO RESIDENTIAL LAVINGTON

As at May-2023

Contractor: Hari International
Project Start Date: 23rd February, 2021
Expected Construction Period: 169 Weeks
Project Outline: Construction of 120 units in Lavington / Construction of a 3 floors commercial hub
48%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
•Site protection and scaffolds installation to the external areas of the site done 100%.
•Site hoarding to the upper floors to be done progressively.
•Formworks and reinforcement for columns to the 4th floor done 90%.
•Casting of the 5th floor slab to be done 100%
•Reinforcement and formworks to the lift walls to the 4th floor ongoing at 30%.
•Formworks and reinforcement work for columns to the 6th floor to be done 90%.
•Slab screed works and protection completed.
•Preparation of walling works

KENZI

As at May-2023

Contractor: Nels Enterprise Limited
Project Start Date: October 2021
Expected Construction Period: 140 Weeks
Project Outline: Construction of 112 units, 5 parking levels at Westland’s church Road
31%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
•Reinforcement, formworks and casting of columns to the ground floor done 90%.
•Columns to 1st floor to be done 100%
•Casting of the basement 02 slab completed.
•Casting of the ground floor slab will be done 100%.
•Retaining walls casting done 80%
•Retaining walls casting to be 100% done.

COVO COMMERCIAL LAVINGTON

As at May-2023

Contractor: Hari Internationnal
Project Start Date: 23rd February 2021
Expected Construction Period: 64 Weeks
Project Outline: Construction of a 3 floors commercial hub
98%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
•Plaster works completed in the all floors
•Paint works to be done 90% in all sections awaiting final paint works.
•Mechanical and electrical 2nd fixes done 40% on ground and first floors.
•Common areas electrical and mechanical installations to be done 80%
•Preparation for installation of the lift done 90%
•Lift installation works to be done 40%
•Installation of roller shutter doors ongoing at 20%.
•Roller shutter doors to be 100% complete.
•External void steel laser cut finish done 20%.
•External finish laser cut void panels to be 100% done.
•Back up genset area reinforcement works in progress.
•Backup genset delivery and installations to be 30% done
• Electricity application and installation in process including installation of poles on the road reserve
•Electricity connection to the building to be done 50%
•Tile sample installation done for approval by consultants.
•Tiling works to be done 40% in entrances , corridors and common areas.