KENZI RESIDENCE

As at Mar-2024

Contractor: Nels Enterprises Ltd.
Project Start Date: October 2021
Expected Construction Period: 140 Weeks
Project Outline: Construction of 112 Units, 5 parking levels at Westland's School Lane Road.
33%%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Decking formwork to the 13th Typical floor slab was 100% done. Steel cutting, bending, and fixing to the 13th typical floor slab was done 100%. Steel fixing to columns projecting to the 14th floor is 100% done.
Steel fixing to columns projecting to the 15th & 16th floors is to be done 100%.
Formwork to the vertical members projecting to the 14th floor: columns, shear walls, and lift shafts were done 100%.
Formwork to the vertical members projecting to the 15th & 16th floor: columns, shear walls and lift shafts to be 100% done.
The casting of all the columns and shear walls was 100% done. Decking formwork for the 14th-floor slab was done 100%. Casting of the 14th typical floor slab has been achieved 100%.
Casting of all the columns and shear walls is to be done 100%
Walling and partition of the basement floor levels were done 100% 1st to 9th Floor walling has been achieved 100%
10th Floor walling is expected to be achieved 100%.
Plaster works on the 1st to 6th floor progressed up to 95% Plastering to the 7th floor is currently at 50%

CICADA CREST APARTMENTS

As at Mar-2024

Contractor: Johkab Enterprises Ltd.
Project Start Date: 1st March 2019
Expected Construction Period: 112 Weeks
Project Outline: 120 Units: 2 Blocks each with 60 units in Kilimani.
91%%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Walling to the balconies has been completed 100% Walling to the ducts along the common areas for the 13th and 14th floors has been completed 100%
Walling on Common areas is expected to be 100% done from the 15th floor
Plaster works on 15th-floor units has been achieved 100%
Plaster works on all exterior balconies are expected to be done 100%
Plaster ongoing on common areas to the 12th, 13th, and 14th floors has been fully achieved 100%.
Completion of plaster works to all common areas, and major voids expected to be 100%
External plaster to all faces is 100% done External plaster to the four balconies is ongoing at 85% Scaffolding and plaster works to the major voids are currently ongoing at 50%
External plaster works expected to be 100% done on all sides
Electrical First fix on units on the 15th floor is 100% done Fixing of CU units ongoing on 11th and 12th floor at 100% Plumbing First fix on units on the 15th floor is 100% done and tested

COVO RESIDENTIAL - LAVINGTON

As at Mar-2024

Contractor: Hari International
Project Start Date: 23rd Feb 2021
Expected Construction Period: 35 Weeks
Project Outline: Construction of 17 Typical Residential floors
48%%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Casting of the 10th floor slab was done 100% Preparations of Columns Reinforcements, Formworks, and casting to columns projecting to the 11th-floor slab have been done 100%.
Preparations of Columns Reinforcements, Formworks, and casting to columns projecting to the 11th and 12th Floor slab have been done 100%.
Walling to the 7th and 8th typical floor is 100% done.
Walling to the 8th and 9th typical floor is expected to be 100% done.
Mechanical and Electrical first fixes to 1 typical slab and walls are 100% done.
Mechanical and Electrical first fixes to 11th and 12th typical slab and walls are 100% done.

COVO SQUARE - LAVINGTON

As at Mar-2024

Contractor: Hari International
Project Start Date: 23rd Feb 2021
Expected Construction Period: 35 Weeks
Project Outline: Construction of a 3 floor commercial Hub
48%%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
The transformer has been delivered to the site & installation works are in progress at 30%
Installations of Lights to both the first and second floor are expected to be done 100%.
Gypsum work is ongoing at 95% to the first and 30% to the second floors.
Completion of Gypsum installations on ground, first and second-floor walkways to be done 100%.
The staircase railing and balustrading have been completed 100%. Washroom fittings and partitioning is 100% done.
The gypsum ceiling, washroom partitions, and light fixtures will be done.
Installation of wash hand basins to washrooms progressing at 50%