CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Decking formwork to the 13th Typical floor slab was 100% done.
Steel cutting, bending, and fixing to the 13th typical floor slab was done 100%.
Steel fixing to columns projecting to the 14th floor is 100% done.
Steel fixing to columns projecting to the 15th & 16th floors is to be done 100%.
Formwork to the vertical members projecting to the 14th floor: columns, shear walls, and lift shafts were done 100%.
Formwork to the vertical members projecting to the 15th & 16th floor: columns, shear walls and lift shafts to be 100% done.
The casting of all the columns and shear walls was 100% done.
Decking formwork for the 14th-floor slab was done 100%.
Casting of the 14th typical floor slab has been achieved 100%.
Casting of all the columns and shear walls is to be done 100%
Walling and partition of the basement floor levels were done 100%
1st to 9th Floor walling has been achieved 100%
10th Floor walling is expected to be achieved 100%.
Plaster works on the 1st to 6th floor progressed up to 95%
Plastering to the 7th floor is currently at 50%