CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
• Othaya Road alucobond and aluminum works completed 99%
• Othaya Road alucobond and aluminum works completed 100%
• Ground floor shops aluminum framings and glass installation done 98%.
• Front shops aluminum and glass installation to be 100%.
• Gitanga Road Alucobond & Aluminum works done 99%.
• Gitanga Road Alucobond & Aluminum works to be done 100%.
• Paint works on ground 1st & 2nd floors done 90%
• Paint works to ground floor walls to be 100%
• Basement floor wall and ceiling plaster works done 95%.
Basement floor walls and ceiling plaster works to be done 100%.
• Waterproofing of the 3rd floor completed and screeding done 96%.
• Waterproofing and Screeding of the 3rd floor roof slab to be 100% done.
• External civil works done on Gitanga & Othaya side on the road reserve done 99%.
• External civil works on the road reserve to be 100% complete.
• Final manhole connection to be complete to the final manhole
• Manhole covers installation for all external parking area manholes.
RESIDENTIAL PART
• Casting of the amenities floor completed
• Casting of the 4th & 5th floor slabs and preparation for the subsequent scopes.
• Contractor mobilizing materials and equipment to site for works to proceed with speed.
• Protection of site from falling debris and installation of hoisting equipment.
• Waterproofing of the floors to prevent water ingress done.
• Mechanical installation on the 3rd floor to drain water pooling on the upper slabs.