CICADA CREST APARTMENTS

As at Mar-2023

Contractor: Skysite construction Group LTD
Project Start Date: 1st March 2019
Expected Construction Period: 188 weeks
Project Outline: Construction of 120 units: two blocks each with 60 units in Kilimani
89%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
• Casting of columns, the 14th floor section B to be 100% done.
• Casting of 14th floor section B slab to be 100% done
• Formworks and reinforcement to the 14th floor wing B done 90%.
• Formworks and reinforcement to 16th floor slab wing A to be 100% done.
• Mechanical and electrical first fixes ongoing.
• Mechanical first fixes to the 16th floor wing A slab to be done 100%.
• Walling on the 8th typical floor done 85%
• Walling on the 9th & 10th typical floor block A & B to be 100% done.
• Lift walls done 95% to the 14th floor.
• Lift walls to be casted to be casted to the 14th floor level.
• Plaster works to the 7th floor units Section A & B 25% done
• Plaster works to the floor units to be on the 8th floor to be 100%.

COVO LAVINGTON COMMERCIAL/RESIDENTIAL

As at Mar-2023

Contractor: Wadia Construction Co. Limited
Project Start Date: 23rd February. 2021
Expected Construction Period: 116 weeks
Project Outline: Construction of 120 units in Lavington / Construction of a 3 floors commercial hub
48%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
• Othaya Road alucobond and aluminum works completed 99%
• Othaya Road alucobond and aluminum works completed 100%
• Ground floor shops aluminum framings and glass installation done 98%.
• Front shops aluminum and glass installation to be 100%.
• Gitanga Road Alucobond & Aluminum works done 99%.
• Gitanga Road Alucobond & Aluminum works to be done 100%.
• Paint works on ground 1st & 2nd floors done 90%
• Paint works to ground floor walls to be 100%
• Basement floor wall and ceiling plaster works done 95%.
Basement floor walls and ceiling plaster works to be done 100%.
• Waterproofing of the 3rd floor completed and screeding done 96%.
• Waterproofing and Screeding of the 3rd floor roof slab to be 100% done.
• External civil works done on Gitanga & Othaya side on the road reserve done 99%.
• External civil works on the road reserve to be 100% complete.
• Final manhole connection to be complete to the final manhole
• Manhole covers installation for all external parking area manholes.
RESIDENTIAL PART • Casting of the amenities floor completed
• Casting of the 4th & 5th floor slabs and preparation for the subsequent scopes.
• Contractor mobilizing materials and equipment to site for works to proceed with speed.
• Protection of site from falling debris and installation of hoisting equipment.
• Waterproofing of the floors to prevent water ingress done.
• Mechanical installation on the 3rd floor to drain water pooling on the upper slabs.

KENZI

As at Mar-2023

Contractor: Nels Enterprise Limited
Project Start Date: October 2021
Expected Construction Period: 118 weeks
Project Outline: Construction of 112 units, 5 parking levels at Westland’s church
30%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
• Reinforcement, formworks and casting Collums to basement 02 done 70%
• Basement 02 slab casting of slab to be done 100%
• Basement 03 retaining walls reinforcement and casting done 40%.
• Basement 03 retaining walls casting to be done 100%.
• Lift walls casting done on basement 03
• Lift walls to basement 02 to be done 60%.