CICADA CREST APARTMENTS

As at Jun-2023

Contractor: Johkab Enterprises
Project Start Date: 1st March 2019
Expected Construction Period: 160 weeks
Project Outline: Construction of 120 units: two blocks each with 60 units in Kilimani
90%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
• Casting of columns projecting to 16th floor, wing B at 75%.
• Casting of 16th floor section B slab to be 100% done by 22nd July, 2023.
• Walling on the 11th typical floor done 85% section B and Walling on 8th typical floor Section A done 87%
• Walling on the 11th & 12th typical floor block A & B to be 100% done
• Mechanical and electrical first fixes ongoing at 9th and 10th floor.
• Walling on the 11th & 12th typical floor block A & B to be 100% done by 17th July, 2023.
• Plaster works to the 7th floor units Section A & B 75% done.
• Plaster works in Section A & B to be 100% done.
• Lift walls done 95% to the 16th floor.
• Lift walls done 100% to the 16th floor.

COVO RESIDENTIAL

As at Jun-2023

Contractor: Hari International
Project Start Date: 23rd February, 2021
Expected Construction Period: 169 Weeks
Project Outline: Construction of 120 units in Lavington
48%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
• Casting to the 5th floor slab and preparation for the subsequent scopes.
• Casting of all columns were achieved according to design specifications.
• Contractor is expected to deliver fourth floor slab
• Casting to the 5th floor slab and preparation for the subsequent scopes.
• Material delivery to site includes: Fabricated formwork, reinforcement to slab and swimming pool area.
• Mobilisation by the new contractor is at 100%
• Hoarding of site has been achieved 100%

COVO COMMERCIAL

As at Jun-2023

Contractor: Hari International
Project Start Date: 23rd, Feb 2021
Expected Construction Period: 64 Weeks
Project Outline: Construction of a 3 floors commercial hub
98%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
• Plaster of the basement walls achieved 100%
• Plaster repairs to the 1st & 2nd floor units and corrido to be completed.
• All entrance gates have been installed with automated roller shutters and decorative metal screen.
• Tiling works on ground floor walkways to be done.
• Cable management in the ducts are ongoing.
• Fixing and laying of cable trays beneath the ceiling is 100% completed.
• Generator slab has been successfully reinforced.
• Stacking of down & waste pipes 100% completed.

KENZI

As at Jun-2023

Contractor: Nels Enterprise Limited
Project Start Date: October 2021
Expected Construction Period: 140 weeks
Project Outline: Construction of 112 units, 5 parking levels in Westland’s School Lane
32%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
• Columns to first floor were casted: 85%
• Casting of first floor slabs for both sections to be done 100%
• The contractor has embarked on formwork to first floor slab: at 75%.
• The formwork to first floor slab to be done 100%.
. Preparation of retaining wall formwork, steel fixing and casting from Basement 1 to ground floor.
. Lift shaft from basement 1 to ground floor done 100%
. Lift shaft to be done to rooftop.