CICADA CREST APARTMENTS

As at Jul-2023

Contractor: Johkab Enterprises Ltd
Project Start Date: 1st March, 2019
Expected Construction Period: 160 Weeks
Project Outline: Construction of 120 units: two blocks each with 60 units in Kilimani
91%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Setting up of column formwork and steel fixing to the 16th Floor is 97% done.
Columns proceeding to carry water tanks will be 100% complete for the entire project.
Formwork and reinforcement to the 16th floor slab (Roof) for wing B to be done 97%.
Roof slab carrying water tanks will be 100% complete for the entire project.
Mechanical and electrical first fixes on the 15th floor slab for wing B is 98% done.
Mechanical first fixes to the 16th floor wing A & B at the rooftop to be done 100%.
Walling work on the 12th typical floor is 85% done for both Wing A & B.
Walling on the 13th & 14th typical floor block A & B to be done 100%
Lift walls are 100% done.
Machine Room for the lifts will be done 100% by the lift supplier.
Plaster works to the 7th floor units Section A & B 25% done.
Plaster works to the 7th floor units Section A & B to be done 100%

KENZI

As at Jul-2023

Contractor: Nels Enterprise Limited
Project Start Date: October 2021
Expected Construction Period: 140 Weeks
Project Outline: Construction of 112 units, 5 parking levels at Westland’s School Lane
33%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Decking of the second floor slab is 100% done
Reinforcement, formworks and casting Columns to second floor are done 100%
Lift walls casting is 100% done on the first floor.
Lift walls to basement 02 to be done 100%.
Reinforcement, formworks and casting Shear walls and lift shaft to second floor are done 100%
Reinforcement, formworks and casting of the swimming pool walls have been done 100%.
Pool deck slab formwork ongoing

COVO COMMERCIAL

As at Jul-2023

Contractor: Hari International
Project Start Date: 23rd February. 2021
Expected Construction Period: 64
Project Outline: Construction of a 3 floors commercial hub
98%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
L.V Meter board manufacturing and delivering to site is 95% done.
Delivery of meter boards will be done 100%
Pipe network Distribution to all shops is done 99%.
Fittings of gate valves and plumbing accessories to be 100% done.
External Manholes, and storm water disposal garting to the open channel done 100%
All Manhole covers installation for all external parking area manholes
Preparation for tiling works on the ground floor walkways is ongoing.
Tiling works on ground, first and second floor walkways to be done.
Paint works at basement B01 and repair works at 1st and 2nd floors done 75%
Repair of Paint works to Basement, ground, first and second floor walls to be 100%.
Basement floor walls and ceiling plaster works were 100% done.
Basement floor wall and ceiling paint works to be completed.

COVO RESIDENTIAL

As at Jul-2023

Contractor: Hari International
Project Start Date: 23rd February. 2021
Expected Construction Period: 169 Weeks
Project Outline: Construction of 120 units in Lavington
48%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Casting of columns projecting to 5th floor slabs are 26% done.
Columns proceeding to the roof slab will be 100% complete for the entire project.
Steel fixing of the 4th floor slab was 100% done according to design specifications.
Casting to the 5th floor slab and preparation for the subsequent scopes.
commenced by preparation of surface and steel fixing ongoing.
Protection of the site from falling debris and installation of hoisting equipment.