CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
L.V Meter board manufacturing and delivering to site is 95% done.
Delivery of meter boards will be done 100%
Pipe network Distribution to all shops is done 99%.
Fittings of gate valves and plumbing accessories to be 100% done.
External Manholes, and storm water disposal garting to the open channel done 100%
All Manhole covers installation for all external parking area manholes
Preparation for tiling works on the ground floor walkways is ongoing.
Tiling works on ground, first and second floor walkways to be done.
Paint works at basement B01 and repair works at 1st and 2nd floors done 75%
Repair of Paint works to Basement, ground, first and second floor walls to be 100%.
Basement floor walls and ceiling plaster works were 100% done.
Basement floor wall and ceiling paint works to be completed.