Roseville Apartments

Kilimani

Contractor: Lexis International
Project Start Date: December/2018
Expected Construction Period: 129 weeks
Project Outline: Construction of 90 units in Kilimani
91%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Shell construction of floors slabs completed up to the 17th floor slab. (Amenities floor)
Plaster finishes of the amenities floor
Plaster works to the building done up to 14th floor 100%
Plaster works of the 15th floor to be 100% done
Walling construction done up to 15th floor done 100%
Walling of the amenities floor areas on the 16th
Internal plaster works 100% done from basements to the 14th floor
Internal plaster to the 15th floor to be 100% done
First Fixes electrical & Mechanical installations on 14th floor done 100%
First Fixes electrical & Mechanical installations on 15th floor to be done 100%
Building finishes ongoing from up to the 13th floors
Building finishes to be done 100% from 1st to 14th floor
External plaster works 97% done from the basement to 14th floor
External plaster to be done 100% from 14th &15th floor
Casting of the parapet walls stub columns at the 17th floor 100%
Formworks & reinforcement to the 17th floor slab done 100%

Cicada Crest Apartments

Kilimani

Contractor: Skysite construction Group LTD
Project Start Date: March/2019
Expected Construction Period: 114 Weeks
Project Outline: Construction of 120 units: two blocks each with 60 units in Kilimani
53%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Casting of the 6th floor block A 100% done
Casting of 7th floor slab blocks A to be done 100%
Casting of columns to the 7th floor Block A done 100%
Casting of columns to the 8th floor block A to be 100%
Formwork & reinforcement on 7th floor slab Block A ongoing at 80%.
Formwork, reinforcement & casting on 7th floor slab Block A to be 100% done
Lift walls casted 100%. from basement to 6th floor
Lift walls to be casted to the 7th floor
Walling on the 2nd typical floor is 100% &. 3rd typical floor is 50%
Walling on the 3rd & 4th typical floor to be 100%
Plastering on 2nd & 3rd floor walls, beams and columns 60% complete Block A&B
Plastering on 2nd & 3rd floor walls, beams and columns 100% complete Block A&B
Formwork, reinforcement & casting on 6th floor Block A 100% Done

COVO Residence

Lavington

Contractor: Skysite construction Group LTD
Project Start Date: Februrary/2021
Expected Construction Period: 22 Weeks
Project Outline: Construction of Residential and Commercial Section
07%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Backfilling works on the commercial section 100% Done
Backfilling for the residential section to be 100% done
Casting of bases on commercial section 100% done
Casting of basement 02 slab on residential to be done 100%
Casting of reinforced concrete retaining wall done 50% on the residential section
Casting of reinforced concrete retaining wall to be done 100% on the residential section
Formworks, reinforcement to Basement 01 on Commercial Section Done 100%
Formworks, reinforcement to Basement 02 on the residential section to be done 100%
Blinding on residential section for the raft foundation done 100%
Casting of the raft foundation on the residential section to be 100% done
Skin wall construction on the Residential 80% done
Skin wall construction on the residential section to be done 100%
Casting of basement 02 slab done 100% on commercial side