CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Shell construction of floors slabs completed up to the 17th floor slab. (Amenities floor)
Plaster finishes of the amenities floor
Plaster works to the building done up to 14th floor 100%
Plaster works of the 15th floor to be 100% done
Walling construction done up to 15th floor done 100%
Walling of the amenities floor areas on the 16th
Internal plaster works 100% done from basements to the 14th floor
Internal plaster to the 15th floor to be 100% done
First Fixes electrical & Mechanical installations on 14th floor done 100%
First Fixes electrical & Mechanical installations on 15th floor to be done 100%
Building finishes ongoing from up to the 13th floors
Building finishes to be done 100% from 1st to 14th floor
External plaster works 97% done from the basement to 14th floor
External plaster to be done 100% from 14th &15th floor
Casting of the parapet walls stub columns at the 17th floor 100%
Formworks & reinforcement to the 17th floor slab done 100%