CICADA CREST APARTMENTS

As at Jan-2023

Contractor: Skysite construction Group LTD
Project Start Date: 1st March 2019
Expected Construction Period: 180 weeks
Project Outline: Construction of 120 units: two blocks each with 60 units in Kilimani
88%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
• Formworks to 13th floor wing B done 100%.
• Formworks to the 13th floor slab to be 40% done.
• Casting of columns the 13th floor section B to be 100% done.
• Casting of columns the 13th floor section B to be 70% done.
• Reinforcement for 13th floor wing B done 10%.
• Formworks to columns to the 13th floor to be 100% done.
• Walling on 10th typical floor Section done 80%.
• Walling on the 10th typical floor block A to be 100% done.
• Lift walls done 90% to the 14th floor.
• Lift walls to be casted to be casted to the 14th floor level.
• Plaster works to the 7th floor units Section A & B 90% done.
• Plaster works to the floor units to be on the 8th floor to be 100%.
• Showhouse done 100% for inspection by clients.
• Furniture installation in the showhouse to be done.

COVO RESIDENTIAL

As at Jan-2023

Contractor: Skysite construction Group LTD
Project Start Date: 23rd February. 2021
Expected Construction Period: 120 Weeks
Project Outline: Construction of 120 units in Lavington
47%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
• Casting of the amenities floor completed.
• Formworks, reinforcement and casting works of the 4th floor slab to be 70% done.
• Arrangements for procurement of materials for subsequent floors.
• Delivery of the required materials to support ongoing works to be underway.
• Waterproofing of the floors to prevent water ingress
• Screeding of the waterproofed floors.

COVO COMMERCIAL

As at Jan-2023

Contractor: Skysite construction Group LTD
Project Start Date: 23rd February, 2021
Expected Construction Period: 116 weeks
Project Outline: Construction of a 3 floors commercial hub
98%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
• Othaya Road alucobond and aluminum works completed 99%
• Othaya Road alucobond and aluminum works completed 100%
• Ground floor shops aluminum framings and glass installation done 70%.
• Front shops aluminum and glass installation to be 100%.
• Gitanga Road Alucobond & Aluminum works done 98%.
• Gitanga Road Alucobond & Aluminum works to be done 100%.
• Walling & plaster works on 1st & 2nd floor shop units completed.
• Paint works to ground floor walls to be 70%.
• Paint works on ground 1st & 2nd floors done 50%
• Plaster works on Ground, 1st & 2nd floor shop units to be complete and paint works to be 100%.
• Basement floor wall and ceiling plaster works done 95%.
• Basement floor wall and ceiling plaster works to be done 100%.
• Floor screeding of the 1st & 2nd floor common areas completed.
• Screeding of 3rd floor slab done to be 100% done.
• External civil works done on Gitanga & Othaya side on the road reserve done 95%.
• External civil works on the road reserve to be 100% complete.
• Sewer connection to the main line done to the last manhole.
• Final manhole connection to be complete to the last manhole.

KENZI

As at Jan-2023

Contractor: Skysite construction Group LTD
Project Start Date: October 2021
Expected Construction Period: 118 weeks
Project Outline: Construction of 112 units, 5 parking levels at Westland’s church Road.
28%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
• Raft section reinforcement, formworks and casting completed.
• Casting of basement 03 to be 100% done.
• Raft beams casting done 100%
• Columns reinforcement, formworks and casting for the back section to be 80% done.
• Procurement arrangements for concrete to cast the raft section made.
• Formworks , reinforcement and casting of basement 02 back section to be 50% done.