CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
• Othaya Road alucobond and aluminum works completed 99%
• Othaya Road alucobond and aluminum works completed 100%
• Ground floor shops aluminum framings and glass installation done 70%.
• Front shops aluminum and glass installation to be 100%.
• Gitanga Road Alucobond & Aluminum works done 98%.
• Gitanga Road Alucobond & Aluminum works to be done 100%.
• Walling & plaster works on 1st & 2nd floor shop units completed.
• Paint works to ground floor walls to be 70%.
• Paint works on ground 1st & 2nd floors done 50%
• Plaster works on Ground, 1st & 2nd floor shop units to be complete and paint works to be 100%.
• Basement floor wall and ceiling plaster works done 95%.
• Basement floor wall and ceiling plaster works to be done 100%.
• Floor screeding of the 1st & 2nd floor common areas completed.
• Screeding of 3rd floor slab done to be 100% done.
• External civil works done on Gitanga & Othaya side on the road reserve done 95%.
• External civil works on the road reserve to be 100% complete.
• Sewer connection to the main line done to the last manhole.
• Final manhole connection to be complete to the last manhole.