CICADA CREST APARTMENTS

As at Feb-2024

Contractor: Johkab Enterprises Ltd.
Project Start Date: 1st March 2019
Expected Construction Period: 112 Weeks
Project Outline: Construction of 120 Units: 2 Blocks each with 60 units in Kilimani.
91%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Walling to the 15th Floor has been completed 100%
Walling on Common areas is expected to be 100% done from the 13th to 15th floor
Walling on Common areas is 100% done from the 10th to 12th floor Walling to the balconies are ongoing at 80%
Walling to the balconies to be done 100%
Plaster works ongoing at 15th-floor units at 80%
Completion of plaster works to all units expected to be 100%
Plaster ongoing on common areas on the 10th and 11th floors at 75% and 100% done on the 7th to 9th floors.
Plaster to common areas wall from 12th to 15th floor is expected to be done 100%
External plaster on one face is 100% done External plaster to the four balconies is ongoing at 30%
External plaster works expected to be 100% done on all sides

KENZI RESIDENCE

As at Feb-2024

Contractor: Nels Enterprises Ltd.
Project Start Date: October 2021
Expected Construction Period: 140 Weeks
Project Outline: Construction of 112 Units, 5 parking levels at Westland's School Lane Road.
33%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Decking formwork to the 12th Typical floor slab was 100% done.
Steel fixing to columns projecting to the 14th and 15th floors is to be done 100%.
Steel cutting, bending, and fixing to the 12th typical floor slab was done 100%. Steel fixing to columns projecting to the 13th floor is 100% done.
Formwork to the vertical members projecting to the 13th floor: columns, shear walls, and lift shafts were done 100%.
Formwork to the vertical members projecting to the 14th & 14th floor: columns, shear walls and lift shafts to be 100% done.
The casting of all the columns and shear walls was 100% done. Decking formwork for the 13th-floor slab is in progress at 30%.
Casting of all the columns and shear walls is to be done
Walling and partition of the basement floor levels were done 100%
8th and 9th Floor walling is expected to be achieved 100%.
1st to 7th Floor walling has been achieved 100%
Decking formwork for the 14th and 15th floor slabs will be done 100%. Steel cutting, bending, and fixing to the 14th and 15th-floor slabs will be done 100%.

COVO SQUARE - LAVINGTON

As at Feb-2024

Contractor: Hari International
Project Start Date: 23rd Feb 2021
Expected Construction Period: Construction of a 3 floor commercial Hub
Project Outline: Construction of a 3 floor commercial Hub
48%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Pulling of cables from the Meter Board to all shops has been completed 100%.
Installations of Lights to both the first and second floor are expected to be done 100%.
The transformer has been procured and is expected to be on-site before 20th March 2024.
Gypsum work is already ongoing at 70% for both the first and second floors.
Completion of Gypsum installations on ground, first and second-floor walkways to be done 10%.
The staircase railing and balustrading have been completed 100%. Washroom fittings and partitioning is 100% done.
The gypsum ceiling, washroom partitions, and light fixtures will be done.

COVO RESIDENTIAL - LAVINGTON

As at Feb-2024

Contractor: Hari International
Project Start Date: 23rd Feb 2021
Expected Construction Period: Construction of a 3 floor commercial Hub
Project Outline: Construction of a 3 floor commercial Hub
48%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Preparations of Columns Reinforcements, Formworks, and casting to columns projecting to the 10th Floor slab have been done 100%.
Preparations of Columns Reinforcements, Formworks, and casting to columns projecting to the 11th and 12th Floor slab have been done 100%.
Walling to the 5th and 6th typical floor is 100% done.
Walling to the 7th and 8th typical floor is expected to be 100% done.
Mechanical and Electrical first fixes to 1 typical slab and walls are 100% done.
Mechanical and Electrical first fixes to 11th and 12th typical slab and walls are 100% done.

COVO ARBORETUM

As at Feb-2024

Contractor: NEL Enterprise Ltd
Project Start Date: 10th March, 2024
Expected Construction Period: 35 Weeks
Project Outline: Construction of 120 units in Kileleshwa / Construction of a 3 floors commercial hub
10%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
All pre-commencement documents and compliances have been achieved.
Mobilization and setting up of site office and site shelter are expected to be done.
Tender processes were finalized and the contractor executing works was established.
Excavation works were done 100%