CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Decking formwork to the 12th Typical floor slab was 100% done.
Steel fixing to columns projecting to the 14th and 15th floors is to be done 100%.
Steel cutting, bending, and fixing to the 12th typical floor slab was done 100%.
Steel fixing to columns projecting to the 13th floor is 100% done.
Formwork to the vertical members projecting to the 13th floor: columns, shear walls, and lift shafts were done 100%.
Formwork to the vertical members projecting to the 14th & 14th floor: columns, shear walls and lift shafts to be 100% done.
The casting of all the columns and shear walls was 100% done.
Decking formwork for the 13th-floor slab is in progress at 30%.
Casting of all the columns and shear walls is to be done
Walling and partition of the basement floor levels were done 100%
8th and 9th Floor walling is expected to be achieved 100%.
1st to 7th Floor walling has been achieved 100%
Decking formwork for the 14th and 15th floor slabs will be done 100%.
Steel cutting, bending, and fixing to the 14th and 15th-floor slabs will be done 100%.