CICADA CREST APARTMENTS

As at Aug-2023

Contractor: Johkab Enterprises Ltd
Project Start Date: 1st March 2019
Expected Construction Period: 160 weeks
Project Outline: Construction of 120 units: two blocks each with 60 units in Kilimani
91%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Steel fixing to wing B rooftop slab (16th Floor) slab is 100% done.
Casting of the 16th floor slab is expected to be done 100%
First fixes to both mechanical and electrical services have been achieved partially to the rooftop slab (15th Floor) i.e. 85% done.
Electrical and mechanical first fixes to be done for the roof terrace.
Setting up the walls at 14th floor level has commenced, and the construction of the walls is at 92%.
Completion of structural skeleton and shell i.e. Concrete and Masonry works.
Hacking for both electrical and mechanical provisions in the walls before plaster works commences for 6th ,7 th and 8th floors is currently ongoing at 75%.
Electrical and mechanical first fixes to Roof slab and as for the walls 6th to 9th floor
Start on production of the wooden doors, joinery and aluminium windows.
Sourcing of paints and granting site possession to finishes contractor.

KENZI

As at Aug-2023

Contractor: Nels Enterprises Limited
Project Start Date: October 2021
Expected Construction Period: 140 Weeks
Project Outline: Construction of 112 units, 5 parking levels at Westland’s School Lane Road
33%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Steel fixing to columns projecting to the second floor is 100% done.
Steel fixing to columns projecting to the third and fourth floors are to be done 100%.
Formwork to the vertical members: columns, shear walls and lift shafts were done.
Formwork to the vertical members: columns, shear walls and lift shafts to be 100% done.
Casting of all the columns and shear walls were 100% done.
Casting of all the columns and shear walls are to be done 100%.
Decking formwork for the second-floor slab was 100% done.
Decking formwork for the third and fourth floor slab are to be done 100%.
Steel cutting, bending and fixing to the second-floor slab was done 100%.
Steel cutting, bending and fixing to the third and fourth floor slab to be done 100%.

COVO COMMERCIAL- LAVINGTON

As at Aug-2023

Contractor: Hari International
Project Start Date: 23rd February. 2021
Expected Construction Period: 64 Weeks
Project Outline: Construction of a 3 floors commercial hub
98%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
L.V Meter board was delivered to site and ready to receive Prepaid Meters.
KPLC prepaid meters expected to be delivered 100%.
Pipe network Distribution to all shops is 100% done.
Fittings of gate valves and plumbing accessories to be 100% done.
Waterproofing and Screeding of the planter boxes were 100% done.
Tiling works on ground, first and second floor walkways to be done.
Washroom fittings and partitioning is in progress at 45%.
Gypsum ceiling, washroom partitions and the light fixtures to be done.
Paint work to Basement walls is 100% done.
Paint works to Basement parking markings to be 100% done.

COVO RESIDENTIAL - LAVINGTON

As at Aug-2023

Contractor: Hari International
Project Start Date: 23rd February. 2021
Expected Construction Period: 169 Weeks
Project Outline: Construction of 120 units in Lavington
48%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Preparations of Columns Reinforcements, Formworks and casting to columns projecting to 6th Floor slab is ongoing.
Formwork and casting to 6th floor to be 100% completed.
Walling to the second typical floor is 100% done.
Mechanical and Electrical first fixes to second typical slab and walls are 100% done.
Steel fixing of the swimming pool section is also ongoing.