CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Steel fixing to wing B rooftop slab (16th Floor) slab is 100% done.
Casting of the 16th floor slab is expected to be done 100%
First fixes to both mechanical and electrical services have been achieved partially to the rooftop slab (15th Floor) i.e. 85% done.
Electrical and mechanical first fixes to be done for the roof terrace.
Setting up the walls at 14th floor level has commenced, and the construction of the walls is at 92%.
Completion of structural skeleton and shell i.e. Concrete and Masonry works.
Hacking for both electrical and mechanical provisions in the walls before plaster works commences for 6th ,7 th and 8th floors is currently ongoing at 75%.
Electrical and mechanical first fixes to Roof slab and as for the walls 6th to 9th floor
Start on production of the wooden doors, joinery and aluminium windows.
Sourcing of paints and granting site possession to finishes contractor.