CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Preparations of Columns Reinforcements, Formworks, and casting to columns projecting to the 11th have been done 100%.
Formwork to 11th floor slab was done 100%
Preparations of Columns Reinforcements, Formworks, and casting to columns projecting to the 12th and 13th Floor slab are expected to be 100% done.
Cutting, bending, and fixing of reinforcement steel bars has been achieved 100%
Walling to the 11th and 12th typical floor is expected to be 100% done.
Placing of plumbing and electrical first fixes to slab was achieved 100%
Casting of the 11th floor slab was done 100%
Preparations of column reinforcements, Formworks, and casting to columns projecting to the 12th-floor slab have been done 100%.
Walling to the 10th and 11th typical floor is progressing at 80%.
Plastering to walls at the 1st and 2nd typical floors has been completed 100%
Mechanical and Electrical first fixes to 7th floor walls are 100% done.
Mechanical and Electrical first fixes to the 12th and 13th typical slab and walls are to be done 100%.