CICADA CREST APARTMENTS

As at Apr-2023

Contractor: Johkab Enterprises
Project Start Date: 1st March 2019
Expected Construction Period: 188 weeks
Project Outline: Construction of 120 units: two blocks each with 60 units in Kilimani
89%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
• Casting of columns, the 14th floor section B to be 100% done.
• Casting of 14th floor section B slab to be 100% done
• Formworks and reinforcement to the 14th floor wing B done 90%.
• Formworks and reinforcement to 16th floor slab wing A to be 100% done.
• Plaster works to the 7th floor units Section A & B 25% done.
• Plaster works to the floor units to be on the 8th floor to be 100%.
• Lift walls done 95% to the 14th floor
• Lift walls to be casted to be casted to the 14th floor level.
• Mechanical and electrical first fixes ongoing.
• Mechanical first fixes to the 16th floor wing A slab to be done 100%.

COVO COMMERCIAL

As at Apr-2023

Contractor: Skysite construction Group LTD
Project Start Date: 23rd February, 2021
Expected Construction Period: 116 weeks
Project Outline: Construction of a 3 floors commercial hub
98%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
• Aluminum and alucobond works to the exterior facades done 100%.
• Othaya Road alucobond and aluminum works completed 100%
• Ground floor shops aluminum framings and glass installation done 99%.
• Front shops aluminum and glass installation to be 100%.
• Paint works on ground 1st & 2nd floors done 95%
• Paint works to ground floor walls to be 100%.
• Basement floor wall and ceiling plaster works done 97%.
• Basement floor walls and ceiling plaster works to be done 100%.
• Staircase screed works to the commercial section completed ready for tiling.
• Plaster works on Ground, 1st & 2nd floor shop units to be complete
• 3rd floor waterproofing completed with minor repairs to be done.
• Waterproofing and Screeding of the 3rd floor roof slab to be 100% done including the start of pool deck works
• Internal drainage pipes installation done 80% on both drainage and storm water lines.
• Plaster repairs to the 1st & 2nd floor units and corrido to be completed.
• Preparation for tiling works on the ground floor walkways ongoing
• Tiling works on ground floor walkways to be done.
• Final manhole connection to be complete to the final manhole
• All Manhole covers installation for all external parking area manholes.

KENZI

As at Apr-2023

Contractor: Nels Enterprises Limited
Project Start Date: October 2021
Expected Construction Period: 118 weeks
Project Outline: Construction of 112 units, 5 parking levels at Westland’s church Road
30%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
• Reinforcement, formworks and casting Collums to basement 02 done 100%
• Basement 01 slab casting of slab to be done 100%
• Basement 03 retaining walls reinforcement and casting done 70%.
• Basement 03 retaining walls casting to be done 100%.
• Mechanical and electrical first fixes done on basement 02.
• Basement 01 slab to be cast 100%.
• Lift walls casting done on basement 03 done 100%
• Lift walls to basement 02 to be done 100%.