CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
• Aluminum and alucobond works to the exterior facades done 100%.
• Othaya Road alucobond and aluminum works completed 100%
• Ground floor shops aluminum framings and glass installation done 99%.
• Front shops aluminum and glass installation to be 100%.
• Paint works on ground 1st & 2nd floors done 95%
• Paint works to ground floor walls to be 100%.
• Basement floor wall and ceiling plaster works done 97%.
• Basement floor walls and ceiling plaster works to be done 100%.
• Staircase screed works to the commercial section completed ready for tiling.
• Plaster works on Ground, 1st & 2nd floor shop units to be complete
• 3rd floor waterproofing completed with minor repairs to be done.
• Waterproofing and Screeding of the 3rd floor roof slab to be 100% done including the start of pool deck works
• Internal drainage pipes installation done 80% on both drainage and storm water lines.
• Plaster repairs to the 1st & 2nd floor units and corrido to be completed.
• Preparation for tiling works on the ground floor walkways ongoing
• Tiling works on ground floor walkways to be done.
• Final manhole connection to be complete to the final manhole
• All Manhole covers installation for all external parking area manholes.