CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Preparations of Columns Reinforcements, Formworks, and casting to columns projecting to the 12th, 13th and 14th floor have been done 100%.
Preparations of Columns Reinforcements, Formworks, and casting to columns projecting to the 15th and 16th Floor slab are expected to be 100% done.
Formwork to Columns, lifts shaft, & shear walls projecting to 12th, 13th and 14th floor slab was done 100%
Cutting, bending, and fixing of reinforcement steel bars to Columns, lifts shaft, & shear walls has been achieved 100%
Walling to the 14th and 15th typical floor is expected to be 100% done.
Placing of plumbing and electrical first fixes to 12th, 13th and 14th floor slab was achieved 100%
Casting of the 12th, 13th and 14th floor slab was done 100%
Preparations of column reinforcements, Formworks, and casting to columns projecting to the 15th-floor slab has progressed 30%.
Walling to the 12th and 13th typical floor is progressing at 80%.
Plastering to walls at the 1st and 2nd typical floors has been completed 100%
Mechanical and Electrical first fixes to 7th floor walls are 100% done.
Mechanical and Electrical first fixes to the 12th and 13th typical slab and walls are to be done 100%.